Friday, July 07, 2006

Wires and Tubs

We now have tubs, and some electrical installed. Things really are moving along.

Here is what changed since the last post:

1) Shingles on the porch and the garage are installed.
2) Finishing stone at the patio door is installed.
3) Stairs are now leveled and properly secure
4) Electrical rough in has started.
5) Shower taps have been roughed in.
6) Tubs are installed in the main bath and ensuite bath.
7) Basement floor is poured.
9) Vent fans are now roughed in and the casing for them is installed.


On Monday, our low voltage wiring will be started and the electrical should be near completion.

Here are some recent pictures:

Various Wires:



Ensuite Shower:


Ensuite Tub:


Outside Front:


Main Washroom Tub: